GEA served as an engineering design and environmental compliance consultant
as well as Site Manager providing CM services for site remediation and cleanup.
Two underground diesel and gasoline storage tanks were removed from the VMF site
when a gasoline spill was discovered during the excavation. Services provided by
GEA included:·
 | Construction Management Services· |
 | UST Removal Design· |
 | Site Assessment in accordance with NYSDEC Spots #14· |
 | Soil Sampling and Analysis· |
 | Design and installation of Groundwater Monitoring Wells· |
 | Groundwater Monitoring and NYSDEC compliance reporting· |
 | Utility Survey· |
 | On-site Remediation of Petroleum Contaminated Soils· |
 | Treatment of over 600 tons of contaminated soil using a NYSDEC permitted
on-site thermal desorption treatment system· |
 | Design and Installation of in-situ bioremediation system consisting of a
soil vapor extraction (SVE) system. |
Upon discovery of the spill, GEA conducted sampling and analysis of soils and
groundwater, installation of monitoring wells, secured a reputable contractor
for on-site soil remediation, thereby saving the replacement cost of clean fill,
provided site management services for the soil remediation and successfully
convinced the NYSDEC to approve a natural attenuation plan with groundwater
monitoring, thereby saving the Postal Service the huge expense of long-term
groundwater remediation. About 600 tons of soil were remediated using an on-site
rotary kiln thermal desorber which reduced benzene to near zero levels. The
environmental corrective action work was performed by GEA for the USPS on an
accelerated basis to permit rapid response to minimize the impact of the spill
on groundwater resources.
The VMF site posed several problems that were overcome including:·
 | Very limited space - postal trucks occupied 90% of the site· |
 | Limited access· Postal vehicle traffic· |
 | Presence of on-site utilities· |
 | Proximity (within 100') to a freshwater stream. |
The tank removal and remediation was successfully completed as groundwater
BTEX levels approached NYSDEC groundwater standards. Site closure was achieved
within 12 months with a NFA letter from NYSDEC.
|