Design and Permitting of the upgrade fourteen (14) underground diesel &
No. 6 fuel oil storage tanks with a combined tankage of over 540,000 gallons for
a Major Oil Storage Facility. Project includes subsurface investigation,
installation of soil borings, groundwater monitoring wells, non-destructive
ultrasonic and volumetric tightness testing of tanks, tank design rehabilitation
including tank leak detection and monitoring systems, lining systems, NYSDEC
permitting, preparation of SPCC plan, soils and groundwater sampling and
analysis, preparation of engineering drawings and design and construction
management services for facility upgrade. GEA also prepared engineering designs
for Bioremediation of petroleum contaminated soils.
GEA designed and installed seven (7) groundwater monitoring wells for the
NYCDOC to successfully meet NYSDEC consent order requirements. Staff shown here
monitoring and sampling the wells using a state-of-the-art automatic well
sampling system employing dedicated bladder pumps and portable air compressor.